Status Update - 3/7/19
March 7, 2019
Status Item | Current Status | Previous Status | Comment |
Schedule | yellow | yellow | Training/UAT pushed 3 weeks. |
Resources | green | green | No resource availability issues. |
Financials | yellow | yellow | CO submitted for $31,147 |
Quality | green | green | Quality metric remains green. |
Project Issues | yellow | green | Banner/Axiom Integration data load is significantly delayed. |
Key Deliverables | % | Comments | Timeline |
Requirement Sign-off | 100% | 12/14 | |
Data Model/Mapping | 100% | 1/12 | |
Build | 78% | Sprint 4 (3a): 3/4-3/15 | 3/28 |
Integration | 0% | UTSA reviewing query before load approval | 3/28 |
Training/UAT | 0% | Not Started | 4/22 |